Everything you wanted to know about
CO2 Capture and Storage (CCS), but had no one to ask .
CO2 Capture and Storage (CCS), but had no one to ask .
1. What is CCS?
CO2 Capture and Storage (CCS) describes a technological process by which the carbon dioxide (CO2) generated by large stationary sources - such as coal- fired power plants, steel plants and oil refineries - is prevented from entering the atmosphere.
Thats because it enables at least 90% of these CO2 emissions to be captured, then stored in geological formations safely and permanently deep underground (at least 800m). In fact, it uses the same natural trapping mechanisms which have already kept huge volumes of oil, gas and CO2 underground for millions of years.
Currently, all of the CO2 produced by these large stationary sources is released into the atmosphere directly contributing to global warming.
CO2 Capture and Storage (CCS) describes a technological process by which the carbon dioxide (CO2) generated by large stationary sources - such as coal- fired power plants, steel plants and oil refineries - is prevented from entering the atmosphere.
Thats because it enables at least 90% of these CO2 emissions to be captured, then stored in geological formations safely and permanently deep underground (at least 800m). In fact, it uses the same natural trapping mechanisms which have already kept huge volumes of oil, gas and CO2 underground for millions of years.
Currently, all of the CO2 produced by these large stationary sources is released into the atmosphere directly contributing to global warming.
2. Why is it a critical technology for combating climate change?
CCS is the single biggest lever to combat climate change (compared to, for example, energy efficiency which requires many different actions). In fact, CCS has the potential to address almost half of the worlds current CO2 emissions.
Experts estimate that by 2050, CCS could reduce annual CO2 emissions by 0.6 to 1.7 billion tonnes in the EU and by 9 to 16 billion tonnes worldwide. The upper end of this range would require its application to all fossil fuel power plants and to almost all other large industrial emitters with the large volumes of hydrogen produced used for transport fuel.
3. What other benefits will CCS provide?
In addition to its potential to reduce CO2 emissions on a massive scale, CCS will also provide greater energy security by making the burning of Europes abundant coal reserves more environmentally acceptable and reducing its dependency on imported natural gas. CCS could also facilitate the transition to a hydrogen economy through the production of large volumes of clean hydrogen which that could be used for electricity or transport fuel.
EU demonstration efforts on CCS will not only demonstrate the EUs commitment to delivering on its own CO2 reduction targets, but spur other countries to do the same especially large CO2 emitters, such as China, India and the US. As a global solution to combating climate change, CCS could therefore also give a major boost to the European economy promoting technology leadership, European competitiveness and creating jobs.
4. How does CCS work?
CCS consists of three stages:
i. Capture: CO2 is captured and compressed at the emissions site.
ii. Transport: The CO2 is then transported to a storage location.
iii. Storage: The CO2 is permanently stored in geological formations, deep underground.
Each of these stages capture, transport and storage can be accomplished in different ways.
i. Capture processes:
Post-combustion: CO2 is removed from the exhaust gas through absorption by selective solvents.
Pre-combustion: The fuel is pre- treated and converted into a mix of CO2 and hydrogen, from which the CO2 is separated. The hydrogen is then used as fuel, or burnt to produce electricity.
Oxy-fuel combustion: The fuel is burned with oxygen instead of air, producing a flue stream of CO2 and water vapour without nitrogen; the CO2 is relatively easily removed from this stream.
ii. Transport options:
Pipelines are the main option for large-scale CO2 transportation, but shipping and road transport are also possibilities.
iii. Storage options:
Deep saline aquifers (saltwater-bearing rocks unsuitable for human consumption)
Depleted oil and gas fields (with the potential for Enhanced Oil Recovery)
5. How long has CCS been in existence?
Although there are currently no fully integrated, commercial-scale CCS projects for power plants in operation, many of the technologies that make up CCS have been around for decades:
CO2 capture is already practised on a small scale, based on technology that has been used in the chemical and refining industries for decades.
Transportation is also well understood: it has been shipped regionally for over 17 years, while a 5,000km network has been operating in the USA for over 30 years for Enhanced Oil Recovery.
Small-scale CO2 storage projects have been operating successfully for over a decade, e.g. at Sleipner (Norway), Weyburn (Canada) and In Salah (Algeria). The industry can also build on knowledge obtained through the geological storage of natural gas, which has also been practised for decades.
6. Whats the next step?
CCS technology now needs to be scaled up including full process integration and optimisation with demonstration projects of a size large enough to allow subsequent projects to be at commercial scale. This will also build public confidence in CCS as more and more people see that CO2 storage is safe and reliable.
7. Why should we use CCS, given its link to fossil fuels?
Scientists have confirmed that unless we stabilise CO2- equivalent concentrations at their current level of 450 parts per million (ppm), average global temperature is likely to rise by 2.4ºC to 6.4ºC by 2100. If we fail to keep below 2ºC, devastating and irreversible climate changes will occur.
This means reducing CO2-equivalent emissions by 50% by 2030. But with world energy demand expected to double by 2030 and renewable energies to make up ~30% of the energy mix by this date, only a portfolio of solutions will achieve this goal. This includes energy efficiency, a vast increase in renewable energy and CCS.
Around 750 new coal power plants are already planned for the period 20052018, totaling more than 350 Gigawatt (GW), of which 50 will be in Europe, almost 300 in China, 200 in India and 50 in the US.
8. Why is it so important to deploy CCS as soon as possible?
Time is of the essence. Any delay in the roll-out of CCS could not only lead to unnecessary CO2 emissions but additional costs, as instead of being able to apply it to the current pipeline of coal plants, a retrofit would be required, increasing the cost of achieving the same emissions reduction. With decisions on the building of new power plants being made now in Europe, it is vital that we are not locked into an infrastructure that is not optimised for CCS.
Indeed, every year that CCS is delayed is a missed opportunity to reduce CO2 emissions. Today, we have ~450 parts per million (ppm) CO2 equivalent in the atmosphere, with concentration rising at over 2 ppm per annum. The Intergovernmental Panel on Climate Change states that if we are to avoid major climate change effects, we must not exceed this 450 ppm. Delaying the implementation of CCS by just 6 years would mean CO2 concentrations increasing by around 10 ppm by 2020.
9. If we are at such a critical phase, why isnt it already being deployed?
The incremental costs of the first large-scale CCS demonstration projects will be exceptionally high too high to be fully justifiable to company shareholders.
Thats because all First Movers will incur:
Unrecoverable costs from making accelerated investments in scaling up the technology.
Market risk due to uncertainty over:
a) which CCS technologies will prove the most successful
b) the future CO2 price and
c) construction and operational costs.
Based on an independent study recently undertaken by McKinsey and Company, it is estimated that the total incremental costs of 10-12 CCS demonstration projects would be 7 billion - 12 billion.
Industry has already declared its willingness to cover both the base costs of the power plant (without CCS) and a major portion of the risks of implementing these CCS demonstration activities. Given that it will bring incalculable benefits to both the public and European industry and that these projects are inherently loss-making, public funding has therefore been provided to support 12 industrial-scale CCS projects. Without this, commercialisation will be severely delayed until at least 2030 in Europe.
10. Why are public funds needed for CCS demonstration projects?
Currently, a CCS demonstration project would be a loss-making enterprise for industry, given the current price of implementing and using the technology; the current price of carbon; and uncertainty surrounding long-term viability and profitability. No shareholder can therefore be expected to fund it fully at this stage.
The typical cost of a demonstration project is likely to be in the range 60-90 per tonne of CO2 abated. Recent analyst estimates for Phase II of the European Union Emissions Trading Scheme (EU ETS) range from 30 to 48 per tonne of CO2 and, at this stage, similar levels are assumed beyond Phase II (up to 2030). In this range, the carbon price is insufficient for demonstration projects to be stand-alone, commercially viable.
Assuming that CCS demonstration projects would cost between 60 and 90 per tonne of CO2, and projecting a median carbon price of 35 per tonne of CO2, there is an economic gap of 25-55 per tonne of CO2 per project. This corresponds to around 500 million - 1.1 billion, expressed as a Net Present Value (NPV) over the lifespan of a 300MW size power plant. The range depends on variations in specific project variables, such as capture technology and capex, transport distance and storage solutions.
11. The UK and the Netherlands are well on their way to implementing CCS demonstration projects wont these be enough to make the technology commercially viable?
As it is not yet known which CCS technologies will prove the most successful, it is vital that the full range is tested including higher-risk technologies optimised across projects and locations. As each region has its own challenges, local demonstration is also important in order to maximise public and political support.
As importantly, EU CCS demonstration efforts will ensure that cross-border projects where CO2 is stored in a different country or region to where it is captured are not excluded. As capture and storage locations are unevenly distributed throughout Europe, cross-border pipelines will play a crucial role in the wide-scale deployment of CCS and the development of clusters in major industrial areas as the next key step.
12. How much will it cost to retrofit CCS technology to existing power plants?
In general, retrofitting an existing power plant would lead to a higher cost for CCS, but these are highly dependent on specific site characteristics, including plant specifications, remaining economic life and overall site layout. For this reason, no generalisation or reference case would be meaningful.
There are four main factors likely to drive the cost increase for retrofits:
The higher capex (capital costs) of the capture facility: the existing plant configuration and space constraints could make adaption to CCS more difficult than for a new build.
The installations shorter lifespan: the power plant is already operating so where (for example) a new plant with CCS may run for 40 years, the capture facility of a 20 year-old plant is likely to have only a 20 year life, reducing the efficiency of the initial capex.
There is a higher efficiency penalty, leading to a higher fuel cost when compared to a fully integrated, newly-built CCS plant.
There is the opportunity cost of lost generating time, because the plant would be taken out of operation for a period to install the capture facility.
13. How can we accelerate the building of CCS projects?
Building a CCS project is a lengthy process: a fully integrated project can take 6.5-10 years before it becomes operational. However, Final Investment Decision can only be made once permits have been awarded across the entire value chain. In the case of CO2 storage, this can take as long as 6.5 years. In such a scenario, even a commercial project started as early as 2016 would not itself become operational until 2024.
Ideally, 10-12 CCS demonstration projects should be operational by 2015. The first early commercial projects should be operational by 2020, with the remaining demonstration projects sufficiently advanced for early commercial projects to be ordered from 2020 onwards. Some 80-120 large- scale CCS projects could therefore be operational in Europe by 2030.
There are several ways we can fast-track the building of CCS projects:
Starting a commercial project as early as possible during the building of the demonstration project so that for example build can start after just one year of the demo being in operation.
Accelerating feasibility studies etc.
Making faster investment decisions
Shortening the tender process
Introducing special measures to shorten the permitting process.
Some projects, by their very nature, will of course be quicker to build than others, e.g. retrofitting existing power plants with CCS; using well-known oil and gas fields with infrastructure and seismic data already available; those with only a short distance from the power plant to the storage site, etc.
14. How much CO2 can be captured using CCS?
One 900 MW CCS coal-fired power plant can abate around 5 million tonnes of CO2 a year. If, as projected, 80-120 commercial CCS projects are operating in Europe by 2030, they would abate some 400 million tonnes of CO2 per year.
By 2050, CCS could reduce annual CO2 emissions by 0.6 to 1.7 billion tonnes in the EU and by 9 to 16 billion tonnes worldwide. The upper end of this range would require its application to all fossil fuel power plants and to almost all other large industrial emitters with the large volumes of hydrogen produced used for transport fuel.
15. Isnt more energy utilised where CCS is implemented?
The absolute efficiency penalty, estimated at around 10% for the reference case (meaning plant efficiency drops from 50% to around 40%), drives an increase in fuel consumption and does require an over- sizing of the plant to ensure the same net electricity output.
However, next-generation technology - such as ultra-supercritical 700°C technology for boilers, coupled with drying in the case of lignite - will achieve a 50% level of overall plant efficiency. While this technology is not currently available, it is expected to be when early commercial CCS projects are built around 2020.
16. Where will CO2 be stored?
The regional distribution and cost of storage in Europe will play an important role in any roll-out of CCS. Most experts agree that depleted oil and gas fields and deep saline aquifers have the largest storage potential.
Depleted oil and gas fields
Depleted oil and gas fields are well understood and around a third of total oil and gas field capacity in Europe is estimated to be economically useable for CO2 storage. With an estimated capacity for 10 to 15 billion tonnes of CO2, this is sufficient for the lifetime of around 50 to 60 CCS projects. However, most of these fields are located offshore in northern Europe and the transportation to and storage of CO2 in these fields (excluding capture) is around twice as costly as onshore fields.
Deep saline aquifers
While much less work has been done to map and define deep saline aquifers, most sources indicate that their capacity should be sufficient for European needs overall. Preliminary conservative estimates by EU GeoCapacity indicate that Europe can store some 136 billion tonnes of CO2 - equivalent to around 70 years of current CO2 emissions from the EUs power plants and heavy industry. At the higher end of these estimations, EU GeoCapacity estimates some 380 billion tonnes of CO2 could be stored in Europe alone.
17. Storing enormous quantities of CO2 underground must present some risk?
The geological formations that would be used to store CO2 diffuse it, making massive releases extremely unlikely. Indeed, because the CO2 becomes trapped in the tiny pores of rocks, any leakage through the geological layers would be extremely slow, allowing plenty of time for it to be detected and dealt with. In fact, it would not raise local CO2 concentrations much above normal atmospheric levels.
Higher concentration leaks could come from man-made wells, but the oil and gas industry already has decades of experience in monitoring wells and keeping them secure. Storage sites will not, of course, be located in volcanic areas.
18. But wont CO2 storage increase the likelihood of seismic activity?
A detailed survey takes place to identify any potential leakage pathways before a CO2 storage site is selected. If these are discovered, then the site will not be selected. In areas where some natural seismic activity is already taking place, we can ensure that the pressure on the CO2 does not exceed the strength of the rock by making the volume of CO2 stored relative to that of the storage site. CO2 storage has even proved to be robust in volcanic areas: in 2004, a storage site in Japan endured a 6.8 magnitude earthquake with no damage to its boreholes and no CO2 leakage. But then CO2 has remained undisturbed underground for millions of years despite thousands of earthquakes.
19. How will we know if the CO2 is leaking?
Before a CO2 storage site is chosen, a detailed survey takes place to identify any potential leakage pathways. If these are found to exist then the site will not be selected. In Europe, underground gas storage (natural gas and hydrogen) has an excellent safety record, with sophisticated monitoring techniques that are easily adaptable to CCS. On the surface, air and soil sampling can be used to detect potential CO2 leakage, whilst changes underground can be monitored by detecting sound (seismic), electromagnetic, gravity or density changes within the geological formations.
The risk of leakage through man-made wells is expected to be minimal because they can easily be monitored and fixed, while CO2 leaking through faults or fractures would be localised and simply withdrawn; and, if necessary, the well closed.
20. Who will be liable for CO2 storage sites over the long-term?
As the CO2 will remain stored underground indefinitely, long-term liability will follow the example set by the petroleum industry, whereby the state assumes liability after a regulated abandonment process. Indeed, EU law governing the safe and permanent storage of CO2 has already been approved and is currently being implemented at national level.
21. Large stationary emitters of CO2 also include refineries, steel and cement plants - how are they linked into what the EC is doing?
The EC encourages the deployment of CCS in other sectors, as 25% of all European CO2 emissions addressable by CCS come from refineries and the cement, iron and steel industries.
The European CCS Demonstration Project Network
The EC has established a Network of CCS demonstration projects to generate early benefits from a coordinated European action.
CCS demonstration projects fulfilling minimum qualification criteria are invited to join the Network and benefit from its operations.
The Network allows early-movers to exchange information and experience from large-size industrial demonstration of the use of CCS technologies, to maximise their impact on further R&D and policy making, and optimise costs through shared collective actions.
It is envisaged that, as the Network evolves, its EU-wide, integrating and binding role may be reinforced and complemented by other measures in support of further development of CCS technologies, building towards the establishment of a European Industrial Initiative.
To help fulfil the potential of CO2 Capture and Storage (CCS), the European Commission is sponsoring and coordinating the worlds first network of demonstration projects, all of which are aiming to be operational by 2015. The goal is to create a prominent community of projects united in the goal of achieving commercially viable CCS by 2020.
The CCS Project Network fosters knowledge sharing amongst the demonstration projects and leverage this new body of knowledge to raise public understanding of the potential of CCS. This accelerates learning and ensures that we can assist CCS to safely fulfil its potential, both in the EU and in cooperation with global partners.
CCS Project Network Advisory Forum
To guarantee that the Network is valuable to the wider energy community in Europe, an annual Advisory Forum has been established to review progress and specify the knowledge that can most usefully be generated by the CCS Project Network.- The first Advisory Forum meeting was held in Brussels on 17 September 2010.
Read more.. - The second Advisory Forum Meeting was held on 16 June 2011 in Brussels. Read more..
CCS World News
- 2012-07-18 - Carbon capture would create substantial challenges, witnesses say at energy ...
- 2012-07-18 - Opinions Divided on Climate Change and CCS in Saskatchewan
- 2012-07-18 - Planned Tees CCS project could be in line for EU cash
- 2012-07-13 - Yorkshire leads race for 1.5bn EU carbon capture funding
- 2012-07-16 - Codexis releases enzyme CO2 capture results
- 2012-07-16 - U.S. DOE advancing Hydrogen Energy plant in California
- 2012-07-16 - Yorkshire leads race for 1.5bn EU carbon capture funding ...
- 2012-07-15 - UK Don Valley project leads EU funding bid
- 2012-07-15 - Alberta projects get funding boost
- 2012-07-13 - Don Valley leads UK CCS charge for 1.5bn EU funds
- 2012-07-13 - EU says up to 1.5 billion euros ready for low-carbon investment
- 2012-07-12 - Anglo mines to become carbon neutral, CCS-aware by 2030
- 2012-07-12 - Clean coal tech is ready, but theres a catch
Membership of the CCS Project Network is open to all European projects that are at a sufficient scale and level of maturity that will generate valuable output and knowledge about industrial-scale CCS demonstration.
The application process for membership of the Network is designed to be as simple and transparent as practicable, but sufficiently robust to ensure that all members are large-scale demonstration projects at a similar level of maturity.
Project developers may submit applications at any time to demonstrate that they fulfil the eligibility criteria, can provide evidence of the maturity of the project, commit to knowledge sharing and agree to the Network organisation and procedures. The qualification criteria and application process are described in the Qualification Criteria document. The Network is open to all qualifying projects and will not distinguish between EU-funded and non-EU funded projects.
Eligibility Criteria
Projects in the Network shall have sound plans to demonstrate the full CCS value chain by 2015 and shall fulfil the following technical criteria:- The CCS project shall for a fossil fuel-fired power plant have a minimum gross production of 250MWe before CO2 capture and compression
- The CCS project shall for an industrial plant realise a minimum of 500kt per year of stored CO2
- The CO2 capture rate shall not be less than 85% of the treated flue gas stream
- The project, i.e. the plant to which CCS is applied, shall be located within the European Economic Area (EEA)
Knowledge Sharing
Projects in the Network are committed to knowledge sharing with similar projects and other stakeholders in order to help accelerate CCS deployment and raise public engagement, as described in the Knowledge Sharing Protocol document.Key documents
European CCS Demonstration Project Network Qualification CriteriaEuropean CCS Demonstration Project Network Knowledge Sharing Protocol
Learn more about CCS
To learn more about CCS, please have a look at the following videos, kindly provided by ZEP:http://www.ccsnetwork.eu/index.php?p=videos
CROATIAN CENTER of RENEWABLE ENERGY SOURCES (CCRES)
special tanks to
Daniel Rennie
Global CCS Institute
Actualis, Level 2
21 & 23 Boulevard Haussmann
PARIS 75009 France
Jose Manuel Hernandez
Programme Manager - EU Policies
European Commission
CROATIAN CENTER of RENEWABLE ENERGY SOURCES (CCRES)
0 komentar:
Posting Komentar